Time Bar Clause Waived: City Inn Revisited (Part 2 of 2)

Last Friday’s City Inn v Shepherd Construction judgment is important for its treatment not only of concurrent delay but also of a time bar clause (for our Law-Now on the former: click here).

United KingdomReal Estate and Construction
Rupert Choat
Rupert Choat
Aidan Steensma
Aidan Steensma

Last Friday’s City Inn v Shepherd Construction judgment is important for its treatment not only of concurrent delay but also of a time bar clause (for our Law-Now on the former: click here). Similar clauses are found in construction contracts like the NEC3 (the form of choice for the London Olympics and, it seems, Crossrail). They defeat (usually contractors’) claims that do not meet specified procedural requirements.

The clause in question required the Contractor within ten days of receiving an instruction to give the Architect details of its estimated effect, failing which the Contractor would lose any entitlement to extend the completion date for the works. If the Contractor’s entitlements arising from the instruction were not agreed within five days the Architect might withdraw the instruction or require the Contractor to proceed anyway. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from