ARTICLE · 30 JULY 2021

Third Time Lucky: Supreme Court Allows Recovery Of Liquidated Damages In Triple Point v PTT

Bryan Cave Leighton Paisner
Bryan Cave Leighton Paisner
Contributor
Bryan Cave Leighton Paisner

Bryan Cave Leighton Paisner

UK 2026 Chambers Firm Profile Bryan Cave Leighton Paisner (BCLP) is an international, fully...

View firm profile
Explore more from Bryan Cave Leighton Paisner

Those you of you with an interest in construction law will no doubt have heard of the case of Triple Point v PTT, which concerned whether liquidated damages (LDs) are payable in the event of termination.

United KingdomReal Estate and Construction

Those you of you with an interest in construction law will no doubt have heard of the case of Triple Point v PTT, which concerned whether liquidated damages (LDs) are payable in the event of termination.

The first judgment was given by Jefford J in 2017 and the Court of Appeal gave judgment on the appeal in 2019. The final decision by the Supreme Court has been long awaited… and we now have the answer to one of the trickier questions of construction law.

Background

By way of reminder, PTT Public Company Ltd (PTT) and Triple Point Technology Inc (Triple Point) entered into a contract in 2013. Under the contract, Triple Point agreed to design, install, maintain and license software to help PTT carry out its business in commodity trading in Thailand. The contract was governed by English law. Payment under the contract was by reference to the achievement of milestones. The contract included a completion date for Phase 1 (Phase 1 consisted of nine stages, of which

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.