Those you of you with an interest in construction law will no
doubt have heard of the case of Triple
Point v PTT, which concerned whether liquidated
damages (LDs) are payable in the event of
termination.
The first
judgment was given by Jefford J in 2017 and the Court
of Appeal gave judgment on
the appeal in 2019. The final decision by the Supreme Court has
been long awaited… and we now have the answer to one of the
trickier questions of construction law.
Background
By way of reminder, PTT Public Company Ltd (PTT) and Triple
Point Technology Inc (Triple Point) entered into a contract in
2013. Under the contract, Triple Point agreed to design, install,
maintain and license software to help PTT carry out its business
in commodity trading in Thailand. The contract was governed by
English law. Payment under the contract was by reference to
the achievement of milestones. The contract included a
completion date for Phase 1 (Phase 1 consisted of nine stages, of
which