In the recent case of MW High Tech Projects UK Ltd v Balfour
Beatty Kilpatrick Ltd the Technology and Construction Court
("TCC") reinforced the principles relevant when deciding
whether or not a dispute had crystallised.
Background
The parties contracted in respect of the building of a
laboratory in Hull, with Balfour Beatty Kilpatrick Ltd
("Balfour Beatty") engaged by MW High Tech Projects UK
Ltd ("MW") to carry out mechanical and electrical
works.
The works were delayed. Balfour Beatty intimated five
contractual notices of delay to MW, but no responses were issued by
MW within the 16 week periods required by the parties'
contract.
By letter of 30 July 2019 Balfour Beatty produced an expert
report in support of their claim and increased the extension of
time sought by 71 days to 282 days in total. The letter requested
confirmation within seven days that the extension of time was
accepted.