Share on LinkedInShare on LinkedIn

ARTICLE · 22 JUNE 2020

The TCC Considers Crystallisation Of A Dispute Arising From An Extension Of Time Claim

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

In the recent case of MW High Tech Projects UK Ltd v Balfour Beatty Kilpatrick Ltd the Technology and Construction Court ("TCC") reinforced the principles relevant when deciding whether or not...

United KingdomReal Estate and Construction

In the recent case of MW High Tech Projects UK Ltd v Balfour Beatty Kilpatrick Ltd the Technology and Construction Court ("TCC") reinforced the principles relevant when deciding whether or not a dispute had crystallised.

Background

The parties contracted in respect of the building of a laboratory in Hull, with Balfour Beatty Kilpatrick Ltd ("Balfour Beatty") engaged by MW High Tech Projects UK Ltd ("MW") to carry out mechanical and electrical works.

The works were delayed. Balfour Beatty intimated five contractual notices of delay to MW, but no responses were issued by MW within the 16 week periods required by the parties' contract.

By letter of 30 July 2019 Balfour Beatty produced an expert report in support of their claim and increased the extension of time sought by 71 days to 282 days in total. The letter requested confirmation within seven days that the extension of time was accepted.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from