The Perils Of Milestone Payment - CIMC MBS Ltd V Bennett (Construction) Ltd [Unreported] 18 July 2018

One of the key terms of the Housing Grants Construction and Regeneration Act 1996 (as amended) ...

United KingdomReal Estate and Construction

Background

One of the key terms of the Housing Grants Construction and Regeneration Act 1996 (as amended) is section 110(1)(a): "Every construction contract shall provide an adequate mechanism for determining what payments become due under the contract, and when". Whilst the parties to a contract are able to determine what their payment provisions will be it is important to keep in mind this provision of the Construction Act.

Declaration

In this case the claimant sub-contractor sought a declaration from the Court that the payment terms in their sub-contract were not an adequate mechanism for determining what payments were due and so were unenforceable. They had agreed to design, supply and install pre-fabricated bedroom units for a hotel in London which were to be made in China, shipped to Southampton and then transported and installed in London. The payment terms were not monthly under the JCT contract but instead due at specified milestones:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from