Originally published in April 2003
The draft pre-action protocol for terminal dilapidations claims1 which was prepared by the Property Litigation Association and published in 2002, with the support of the Royal Institution of Chartered Surveyors, is likely to be adopted by the Lord Chancellor’s Department and become one of the pre-action protocols which parties to a dispute are expected to follow under the Civil Procedure Rules, the rules governing the conduct of litigation in England and Wales.
The protocol relates to claims for damages brought by landlords against tenants which are in breach of repairing obligations upon the expiry of their leases. It has been used by parties to dilapidations disputes with the approval of the judiciary for some time and is regarded as best practice in terms of identifying and resolving the relevant issues before cases come to court, sometimes avoiding the need for legal proceedings altogether. A party which refuses to follow the protocol already