The First-tier Tribunal ("FTT") recently arrived at its decision in respect of a Remediation Order (RO) pursuant to section 123 of the Building Safety Act 2022 ("BSA 2022")...

United KingdomReal Estate and Construction

The First-tier Tribunal ("FTT") recently arrived at its decision in respect of a Remediation Order (RO) pursuant to section 123 of the Building Safety Act 2022 ("BSA 2022") and a Remediation Contribution Order ("RCO") under section 124 in respect of Empire Square.

This case is significant for two reasons. Firstly, that the FTT has unequivocally confirmed that RCOs may be used to recoup various costs, including the legal costs incurred in applying for ROs and RCOs. The second that the FTT determines its discretion extends to making and then suspending ROs and RCOs.

Background

The lessees of Empire Square (represented by Mr Zampetti and others) sought a RO against the landlord (Fairhold Athena Limited), in relation to, a number of relevant defects in the building including defective cladding.