In the fast-paced world of construction projects, letters of
intent are a common feature of the contractual landscape. So what
happens if the formal contract being negotiated is never entered
into? We take a brief look at some of the approaches the Courts
have taken in light of a recent decision of the Court of
Appeal.
To view the article in full, please see
below:
Full Article
Where a building project is time-critical (as it often is) and
contractual negotiations are ongoing, it is common for parties to
enter into a letter of intent ("LOI") to
enable the Contractor to commence work before the contract proper
has been finalised. The form and content of LOIs are as varied as
the circumstances in which they may be issued.No doubt it is this
variety that led Robert Goff J in British Steel Corp v
Cleveland Bridge and Engineering Co Ltd (1984) to observe that
there is "no hard and fast answer to the question whether
a letter of intent will give rise to a