In Providence Building Services Ltd v Hexagon Housing Association Ltd [2026] UKSC 1, the Supreme Court allowed an employer's appeal as to the proper interpretation of the JCT Design...

United KingdomReal Estate and Construction

Providence Building Services v Hexagon Housing Association [2026] UKSC 1

Introduction

In Providence Building Services Ltd v Hexagon Housing Association Ltd [2026] UKSC 1, the Supreme Court allowed an employer's appeal as to the proper interpretation of the JCT Design and Build Contract 2016's termination provisions. The immediate issue concerned a contractor's right to terminate for repeated late payment:

"Can the contractor terminate its employment under clause 8.9.4 of the JCT [...] where a right to give the further notice referred to in clause 8.9.3 has never previously accrued?"

The judgment is significant for construction lawyers, given JCT's widespread use and the JCT 2024's adoption of the same termination clause. Lord Burrows' reasoning is also a pithy and authoritative restatement of various matters of wider commercial interest:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from