Most of us with experience of construction contracts of any
description recognise that requests for more money or for longer to
complete the job are commonplace. A good construction contract will
clearly establish the circumstances in which additional time or
money can be allowed, and a basis for measuring any change.
But can a genuine claim for time or money be disallowed because
the party claiming it has not followed the contractual process? In
the recent case of Energy Works (Hull) Ltd v MW High Tech
Projects UK Ltd & Others, it was confirmed that a failure
to follow the agreed process could indeed lead to otherwise robust
claims failing.
A condition precedent, or a time bar, is a clause in a contract
that sets out a condition or an event that must be satisfied or
occur before a right or obligation under a contract comes into
existence. In the case of time or money claims under a contract,
that usually manifests as a requirement to provide a notice