ARTICLE · 14 AUGUST 2017

Subsidy Free: The Planning Consequences Of Larger Schemes

Now that subsidies have ended, there is a question over the impact of the size of a scheme and whether size matters.

United KingdomReal Estate and Construction
Fergus Charlton
Fergus Charlton

When subsidies were available, with the exception of roof mounted solar, the vast majority of solar schemes ranged from 5MW to 49.99 MW

Now that subsidies have ended, there is a question over the impact of the size of a scheme and whether size matters. One might argue that larger schemes are more attractive because they bring more economies of scale, as the legal, planning and consultancy costs and investment in management time are the same regardless of the size of the development. In addition, each development only needs one point of grid connection and one grid connection agreement, so it makes sense to bear this cost across a larger scheme.

Solar farms peaked at 49.99 MW because anything above that level of output requires a Development Consent Order (DCO) rather than a traditional planning permission. While there is much to be said in favour of the DCO application process – which has been positively adopted by the wider national infrastructure sector – it