When subsidies were available, with the exception of roof
mounted solar, the vast majority of solar schemes ranged from 5MW
to 49.99 MW
Now that subsidies have ended, there is a question over the
impact of the size of a scheme and whether size matters. One might
argue that larger schemes are more attractive because they bring
more economies of scale, as the legal, planning and consultancy
costs and investment in management time are the same regardless of
the size of the development. In addition, each development only
needs one point of grid connection and one grid connection
agreement, so it makes sense to bear this cost across a larger
scheme.
Solar farms peaked at 49.99 MW because anything above that level
of output requires a Development Consent Order (DCO) rather than a
traditional planning permission. While there is much to be said in
favour of the DCO application process – which has been
positively adopted by the wider national infrastructure sector
– it