Should Contractors Be Taking Notice Of A Recent Loss And Expense Claim In Scotland?

A Scottish Court of Session decision established that contractual notification requirements for loss and expense claims are conditions precedent. In FES Ltd v HFD Construction Group Ltd, the court ruled that failure to notify as required under clauses 4.20 and 4.21 of the SBC/Q/Scot 2016 contract invalidated the claim. This precedent stresses strict compliance with notice requirements, potentially impacting contractors' ability to recover costs under similar JCT contracts.

United KingdomReal Estate and Construction

A recent decision from the Scottish Court of Session has found that contractual notification requirements for loss and expense claims is a condition precedent.

A condition precedent is a clause that provides that certain contractual obligations will only have effect if certain conditions are met or satisfied. Here, the condition to a claim for loss and expense is valid notification. Steven Smith, B P Collins' dispute resolution partner, who specialises in construction disputes, explores why this decision could be hugely significant for building contractors.

Background

In FES Ltd v HFD Construction Group Ltd, the parties entered into a Scottish Standard Building Contract with Quantities for use in Scotland. (SBC/Q/Scot) (2016 edition). A dispute arose over a claim for an extension of time,,and loss and expense.