Reminder To Have Clearly Agreed Terms Before Starting Work – And Check Limitation Clauses: Will They Be Effective When You Need Them?

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In the recent case of Balfour Beatty Regional Construction Ltd (BB) v Van Elle Ltd [2021], the question before the Technology and Construction Court was whether the sub-contract superseded any prior contractual relationship ...

United KingdomReal Estate and Construction

In the recent case of Balfour Beatty Regional Construction Ltd (BB) v Van Elle Ltd [2021], the question before the Technology and Construction Court (TCC) was whether the sub-contract superseded any prior contractual relationship between the parties, or whether the sub-contract was subject to Van Elle's standard terms and conditions.

Background

BB (known at that time as Mansell Construction Services Ltd) was appointed as main contractor to design and construct a sub-sea cable manufacturing facility at a site in Newcastle owned by Technip Umbilicals Ltd.

BB then engaged the services of Van Elle to carry out piling works between June 2012 and August 2013 for an agreed total price of £1.239 million.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from