Share on LinkedInShare on LinkedIn

ARTICLE · 18 FEBRUARY 2015

Rates And Refurbishments - When Is A Building In Repair?

The question of how to value a building which is undergoing substantial refurbishment came before the Court of Appeal.

United KingdomReal Estate and Construction

The question of how to value a building which is undergoing substantial refurbishment came before the Court of Appeal who ruled yesterday that the Valuation Tribunal had wrongly attributed a rateable value of £1 to offices which had almost all of its internal elements stripped out including the cooling system, all internal and external plant, electrical wiring and had no sanitary fittings. It has ruled on what 'repairs' are but the judgment will not give many investors clarity over what their rates liability could be during refurbishment works.

The case is Newbigin v S J and J Monk. The building was only built in the late 1990s. During the recession the freeholders stripped out the building. It had been vacant for some time.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.