Practical Guidance From The High Court On Interpretation Of "Days" In A Construction Contract

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In Elements (Europe) Ltd v FK Building Ltd,[1] the Technology and Construction Court (TCC) considered the meaning of "days" in a Joint Contracts Tribunal (JCT) subcontract...

United KingdomReal Estate and Construction

In Elements (Europe) Ltd v FK Building Ltd,1 the Technology and Construction Court (TCC) considered the meaning of "days" in a Joint Contracts Tribunal (JCT) subcontract, holding that an interim payment application could be received at any time up to 11.59pm on the required day.

The TCC noted that the parties had settled their dispute after receiving the draft judgment. Nonetheless, it considered it appropriate to hand down the decision given that it relates to the "proper construction" of an important element of a widely used JCT standard form, which had not previously been considered by the courts. We consider below the practical guidance offered by this case as to the Court's interpretation of "days" in circumstances where a contract specifies a day / number of days for performance of an obligation, or service of a notice or application.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from