ARTICLE · 10 MARCH 2025

Postponement Of Works: Valid Variation Or Breach Of Contract?

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

In Grain Communications Limited v Shepherd Groundworks Ltd the Technology and Construction Court (TCC) decided that an employer's decision...

United KingdomReal Estate and Construction

In Grain Communications Limited v Shepherd Groundworks Ltd the Technology and Construction Court (TCC) decided that an employer's decision to postpone works without providing a new commencement date was a valid exercise of its contractual right to instruct a variation and was not a breach of contract that entitled the contractor to damages.

Given the instruction was a variation, Grain Communications Limited (the "Employer"), was not liable to Shepherd Groundworks (the "Contractor") for mobilisation/demobilisation costs or loss of profit that it had allegedly suffered (and that an adjudicator had previously decided it had a common law remedy to).

This decision is significant because it demonstrates the approach the TCC may take in relation to the interpretation of broadly drafted variation clauses in construction contracts.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from