This is entry number 164, first published on 14 September 2010,
of a blog on the implementation of the Planning Act 2008. Click
here for a link to the whole blog. If you would like to
be notified when the blog is updated, with links sent by email,
click here.
Today's entry reports on the disclosure of the preferred
Thames Tunnel route and the launch of consultation on it.
Thames Water has been working on a major project to provide
additional sewage capacity in London. Yesterday, it launched the
first round of public consultation on its proposed 'Thames
Tunnel', which also revealed its preferred route and proposed
land take for shafts to build and access the tunnel.
The Thames Tunnel is to be a 32km tunnel tracking the Thames but
70 metres below ground that will carry sewage, particularly during
heavy rain conditions. At the moment the so-called 'combined
sewer outflows' (CSOs) discharge into the Thames when there is
so much rainwater that the existing system