ARTICLE · 17 SEPTEMBER 2018

Parties Free To Allocate The Risk Of Concurrent Delay In Construction

It is for this reason that parties, as was the case in North Midland, seek to introduce wording to reverse that potential outcome.

United KingdomReal Estate and Construction

This Client Alert discusses the recent decision of the Court of Appeal of England and Wales in North Midland Building Limited v. Cyden Homes Limited [2018] EWCA Civ 1744. The decision involved a bespoke extension of time clause in a construction contract that allocated to the contractor the risk of concurrent delay. The Court of Appeal upheld the first instance decision, confirming that parties to a construction contract are free to allocate the risk of concurrent delay and, if the drafting is sufficiently clear, the "prevention principle" will not invalidate the agreed risk allocation.

Introduction

When negotiating a construction contract, the issue inevitably arises as to how the extension of time provisions will operate when delays happen for a combination of reasons, some of which are the contractor's responsibility and some of which are the employer's.  

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from