ARTICLE · 04 APRIL 2011

No Light At The End Of The Tunnel

A decision in September 2010 caused great concern for developers who either ignored or were unable to resolve rights of light issues before beginning a development.

United KingdomReal Estate and Construction
Danielle Drummond-Brassington
Danielle Drummond-Brassington

A decision in September 2010 caused great concern for developers who either ignored or were unable to resolve rights of light issues before beginning a development.

The case involved a commercial building in Leeds which was bought by a developer with the benefit of planning permission for the addition of two extra floors.  The developer was aware when it bought that the development might interfere with the light available to an adjoining owner.  Negotiations were entered into but no settlement was reached.  The developer pressed ahead and completed the works in July 2009.

The developer tried to conclude any issues by applying for a ruling that the adjoining owner would be entitled to monetary compensation only for the interference but were shocked when the court instead awarded an injunction requiring demolition of the extra floors.  In previous decisions relating to commercial buildings the Court has awarded damages in lieu of injunctions.