No Contractual Definition Of "Force Majeure" Means No Extension Of Time (EoT)...Not Quite.

The times this phrase has headlined the construction industry, you would have thought there is an understanding of what it is and a standard definition incorporated in the main forms of construction contracts...

United KingdomReal Estate and Construction

The times this phrase has headlined the construction industry, you would have thought there is an understanding of what it is and a standard definition incorporated in the main forms of construction contracts (JCT, NEC and FIDIC). In an ideal world this would be the case, but in the current construction industry, no.

There is no standard definition of force majeure in English law, and it was first introduced in Lebeaupin v Richard Crispin and Company [1920] 2 K.B.714, which stated a "force majeure clause should be construed in each case with close attention to the words which precede or follow it, and with a due regard to the nature and general terms of the contract. The effect of the clause may vary with each instrument."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from