ARTICLE · 16 MARCH 2020

Managing The Impact Of The Coronavirus Outbreak On Construction Projects In The UK

With a focus on JCT and NEC standard form Construction Contracts

United KingdomReal Estate and Construction

With a focus on JCT and NEC standard form Construction Contracts

On 5 March 2020, the UK's chief medical adviser announced that the UK was ramping up its "delay" phase measures to slow down the spread of the COVID-19 virus. The government is still considering the measures that would be taken in the "delay" phase but has previously indicated that these could include closing schools, encouraging working from home, and discouraging the use of public transport. 

Despite a relatively limited number of cases having been reported in the UK to date (at the time of writing), the recent jump in the number of daily confirmed cases internationally has raised fears that the outbreak could become a pandemic (when an infectious disease spreads easily from person to person in many parts of the world). The effects of the virus in the UK and internationally both in terms of the rising number affected as well as the preventative measures taken mean that it is now well within the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from