ARTICLE · 04 DECEMBER 2014

Liberty v Cuddy (3): Is The Court Acting As A Bondsman?

The Technology and Construction Court considered a payment of funds into court as an alternative remedy to specific performance to deliver security documentation.

United KingdomReal Estate and Construction

Summary and implications

In the recent decision of Liberty Mercian Limited v Cuddy Civil Engineering Limited [2014] EWHC 3854 (TCC) the Technology and Construction Court (the Court) considered a payment of funds into court as an alternative remedy to specific performance to deliver security documentation.

Liberty Mercian Limited (Liberty) entered into a contract with Cuddy Civil Engineering Limited (CCEL) for works relating to the construction of a new retail plateau which was later terminated.

In fact, CCEL is a dormant company and its group company, Cuddy Demolition and Dismantling Limited (CDDL), was the company carrying out the works. 

On termination of the contract, Liberty alleged that CDDL ought to have been the contracting party and in any event, either CDDL or CCEL were in breach of the contract by failing to provide a parent company guarantee, performance bond and collateral warranties from a consultant in its favour, as required under the contract.