Maintaining records to meet the burden of proof and
demonstrate causation in your construction claim or defence is
essential. It's all on you!
Burden of proof
The burden of proof to be satisfied in construction matters is
in line with civil procedures, namely 'on the balance of
probabilities'. This standard is thought to be vague compared
to the higher standard of proof in criminal cases 'beyond
reasonable doubt'. However, who has the burden of proof may
depend on the circumstances under which a claim arises and the
burden can shift from one party to the other in defence of an
assertion.1
What does this mean in practice?
No matter who is responsible for deciding your claim, whether
that be an Architect, Adjudicator or Arbitrator, you will have to
prove your claim on the balance of probabilities. For example, if
you respond to a claim saying "no, we did not cause delay due
to.you were already very late with." it will require you to
prove that is the case.