Immunity From Enforcement Considered In Enforcement Notice Appeal (Devine v Secretary Of State For Levelling Up, Housing And Communities)

The Appellant purchased a site with a barn in 2000 and undertook various works between 2000 and 2018. In March 2019, the Council issued an enforcement notice alleging...

United KingdomReal Estate and Construction

The Appellant purchased a site with a barn in 2000 and undertook various works between 2000 and 2018. In March 2019, the Council issued an enforcement notice alleging that the works amounted to construction of a new building in breach of planning control.

On appeal, the Appellant argued that the works were for repair and improvement and were complete in 2015, more than four years prior to the date of the enforcement notice (the Relevant Date). The Inspector determined that the works constituted construction of a new building and were not complete prior to the Relevant Date. The High Court and Court of Appeal (CoA) agreed with the Inspector's conclusions.

The CoA considered how the four-year rule under the Town & Country Planning Act 1990 (the Act) should be interpreted and applied. In determining whether the construction of the building had been substantially completed, it was relevant to consider both the building's purpose and the developer's intention.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from