The Appellant purchased a site with a barn in 2000 and undertook
various works between 2000 and 2018. In March 2019, the Council
issued an enforcement notice alleging that the works amounted to
construction of a new building in breach of planning control.
On appeal, the Appellant argued that the works were for repair
and improvement and were complete in 2015, more than four years
prior to the date of the enforcement notice (the Relevant Date).
The Inspector determined that the works constituted construction of
a new building and were not complete prior to the Relevant Date.
The High Court and Court of Appeal (CoA) agreed with the
Inspector's conclusions.
The CoA considered how the four-year rule under the Town &
Country Planning Act 1990 (the Act) should be interpreted and
applied. In determining whether the construction of the building
had been substantially completed, it was relevant to consider both
the building's purpose and the developer's intention.