If You Want To Crack The Whip, Make Sure Your Construction Contract Allows You To Do So

In a recent case the Technology and Construction Court declined to imply into a construction contract an obligation to proceed regularly and diligently with the works, despite the fact that failure to do so gave an express right to terminate the contract.

United KingdomReal Estate and Construction
Navpreet Jandaur
Navpreet Jandaur

In a recent case the Technology and Construction Court declined to imply into a construction contract an obligation to proceed regularly and diligently with the works, despite the fact that failure to do so gave an express right to terminate the contract.

Facts

The case concerned a bespoke groundworks subcontract, which placed an obligation on the subcontractor to complete the works by the contractual completion date. The subcontract included an Activity Schedule containing timescales within which the subcontract works were to be undertaken. There were no milestone dates or sectional completion provisions. It was claimed that the subcontractor was late in the performance of the works against the Activity Schedule. The contractor alleged that the subcontractor's delays caused it loss and sought to withhold amounts otherwise due to the subcontractor. Although the parties had accepted that the Activity Schedule did not establish contractually binding timescales, the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from