You want to undertake works and you appoint a contractor. You then change your mind, and decide to omit some of the works or amend the contract.

United KingdomReal Estate and Construction

You want to undertake works and you appoint a contractor. You then change your mind, and decide to omit some of the works or amend the contract. You will need to consider whether this has an impact on other contractual provisions. In a recent case, the court has ruled that a commercially agreed liquidated damages provision was a penalty.

Unaoil, a company incorporated in the British Virgin Islands brought a case to the High Court against a company called Leighton Offshore incorporated in Singapore in Unaoil Ltd v Leighton Offshore Offshore PTE Ltd [2014] EWHC 2965. The former company has experience in the oil and gas sector principally in 'challenging locations' for matters such as camp solutions, technical workforce etc. for construction / engineering projects, and was appointed (a point which was also debated in the High Court) as a subcontractor of Leighton's, a leading engineering and construction constructor. Both parties entered into a memorandum of agreement