House Of Lords Rules For The First Time On The Housing Grants Act - Withholding Notices Not Required Following Determination Of Contract

In its first ever ruling on the Housing Grants, Construction & Regeneration Act 1996 ('the Act'), the House of Lords has decided in Melville Dundas Ltd v George Wimpey UK Ltd that where a contract has been determined on the grounds of an insolvency event, payment can be withheld despite the absence of an effective notice of withholding.

United KingdomReal Estate and Construction
Greg Richards
Greg Richards

In its first ever ruling on the Housing Grants, Construction & Regeneration Act 1996 ('the Act'), the House of Lords has decided in Melville Dundas Ltd v George Wimpey UK Ltd that where a contract has been determined on the grounds of an insolvency event, payment can be withheld despite the absence of an effective notice of withholding.

The Background

Melville Dundas ('the Contractor') was engaged by Wimpey ('the Employer') to carry out a housing development subject to the Standard Form of Building Contract issued by the Scottish Building Contracts Committee incorporating the JCT Standard Form of Building Contract (1998 Edition). On 16 May 2003, the Contractor should have been paid the sum of approximately £400,000 by way of interim payment certified by the Employer's Agent, this being the final date for payment. No notice of intention to withhold payment had been served. On 22 May 2003 administrative receivers were appointed to the Contractor. On 30 May 2003 the Employer determined