Grove v S&T - The Fate Of Smash And Grab Adjudications Is Decided

In the much discussed judgment of Grove Developments Limited v S&T Limited EWHC 123, Coulson J held that an employer is free to commence a second adjudication to dispute the true valuation of an interim payment application.

United KingdomReal Estate and Construction

In the much discussed judgment of Grove Developments Limited v S&T (UK) Limited [2018] EWHC 123 (TCC), Coulson J held that an employer is free to commence a second adjudication to dispute the true valuation of an interim payment application, provided it has paid the sum stated as due in the interim application. 

Coulson J considered that the decisions in ISG v Seevic and Galliford Try v Estura, which paved the way for 'smash & grab' adjudications, were in fact wrongly decided.

By way of reminder, 'smash & grab' adjudications arise where a contractor makes a payment application for a specific sum and the employer fails to issue a valid payment and pay less notice. The amount specified by the contractor becomes the 'notified sum' and the employer is obliged to pay without the true value of the claim being assessed.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from