In Ravestein B.V. v Trant Engineering Limited [2023], the Technology and Construction Court (TCC) has refused a claimant's permission to appeal an arbitrator's decision under the...

United KingdomReal Estate and Construction

In Ravestein B.V. v Trant Engineering Limited [2023], the Technology and Construction Court (TCC) has refused a claimant's permission to appeal an arbitrator's decision under the Arbitration Act 1996 (Arbitration Act). In doing so, the TCC has issued further guidance on an issue that has been considered by the courts in a line of recent case law (which we discuss further below): namely, the requirements for a valid notice of dissatisfaction, under the New Engineering Contract (NEC) suite of contracts, with an adjudicator's decision.

Introduction

Under the Housing Grants, Construction and Regeneration Act 1996 (Construction Act), adjudicator's decisions are 'interim-binding', i.e. binding until finally determined by litigation, arbitration or by agreement.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from