Follow Up On Be Careful What You Wish For January 2018 Construction Law Update

The matter was heard on appeal in July of this year and the original decision of the TCC was upheld.

United KingdomReal Estate and Construction

North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA Civ 1744 Background

In our January HTML we reported on the decision in the Technology and Construction Court holding that a clause in a construction contract was unambiguous and therefore could not be said to be inoperable by the prevention principle.

The matter was heard on appeal in July of this year and the original decision of the TCC was upheld.

The Claimant, North Midland Building Ltd, was the main contractor for the Defendant, Cyden Homes. Their agreement was based on an amended JCT 2005 contract in which the extension of time clause at 2.25.1 was amended to state '€¦ any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account.' In other words, in the event there is concurrent delay which was caused by the contractor or for which the risk was allocated to him under the building contract, then the contractor would