North Midland Building Ltd v Cyden Homes Ltd [2018] EWCA
Civ 1744 Background
In our January HTML we reported on the
decision in the Technology and Construction Court holding that a
clause in a construction contract was unambiguous and therefore
could not be said to be inoperable by the prevention principle.
The matter was heard on appeal in July of this year and the
original decision of the TCC was upheld.
The Claimant, North Midland Building Ltd, was the main
contractor for the Defendant, Cyden Homes. Their agreement was
based on an amended JCT 2005 contract in which the extension of
time clause at 2.25.1 was amended to state '€¦
any delay caused by a Relevant Event which is concurrent with
another delay for which the Contractor is responsible shall not be
taken into account.' In other words, in the event there is
concurrent delay which was caused by the contractor or for which
the risk was allocated to him under the building contract, then the
contractor would