Judgment was delivered yesterday in Melville Dundas v Wimpey - the first case concerning the Construction Act to reach the House of Lords. The case considers whether the JCT provisions which suspend a contractor’s entitlement to payment in the event of insolvency fall foul of the Act.

United KingdomReal Estate and Construction
Julian Bailey
Julian Bailey

Judgment was delivered yesterday in Melville Dundas v Wimpey - the first case concerning the Construction Act to reach the House of Lords. The case considers whether the JCT provisions which suspend a contractor’s entitlement to payment in the event of insolvency fall foul of the Act. It also raises questions as to when a withholding may be made even though a valid withholding notice was not issued.

Background

  • Wimpey (as developer) entered into a contract with Melville Dundas (as contractor) for the construction of a housing development in Glasgow. The contract was a JCT Standard Form of Building Contract with Contractor’s Design (1998 ed).
    • Melville Dundas made several applications for payment. One payment application was for around £400K. A valid withholding notice was not issued by Wimpey in relation to that application. Ordinarily, the lack of a valid withholding notice would leave Melville Dundas entitled to payment of the full amount.