Final Date For Payment: A Lidl Clarity After Rochford v Kilhan

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In Lidl Great Britain Limited v Closed Circuit Cooling Limited t/a 3CL, the Technology and Construction Court (TCC) considered whether reference to the issue of a VAT invoice...

United KingdomReal Estate and Construction

In Lidl Great Britain Limited v Closed Circuit Cooling Limited t/a 3CL,1 the Technology and Construction Court (TCC) considered whether reference to the issue of a VAT invoice could determine the final date for payment in a construction contract. We summarise some of the issues arising in the case relating to payment under a construction contract.

Background facts

  • Lidl entered into a framework agreement (FA) with 3CL, a contractor providing industrial refrigeration and air-conditioning services. The FA enabled the parties to enter into specific work orders, each constituting a separate contract.
  • 3CL was entitled to make applications for interim payments after achieving defined milestones.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from