FIDIC Notice Requirements: When To Give Notice Of Entitlement

Under the FIDIC Yellow Book Conditions, a contractor must give notice of a delaying event within 28 days or risk losing its entitlement to an extension of time.

United KingdomReal Estate and Construction
David Robertson
David Robertson

Introduction

Under the FIDIC Yellow Book Conditions, a contractor must give notice of a delaying event within 28 days or risk losing its entitlement to an extension of time. This reflects standard practice for international EPC contracts. A properly drafted 'notice condition precedent' will be enforceable (under English law) and can have dramatic consequences for a contractor – in some circumstances leaving the contractor liable for delay liquidated damages even where the project owner is responsible for the delay.

Under the relevant notice clauses in the FIDIC Yellow Book Conditions, notice must be given within 28 days of any event the result of which is that the date for completion 'is or will be delayed'.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from