The Dubai International Finance Centre ("DIFC") Court of Appeal has recently handed down a judgment in which it considered issues such as notices as conditions precedent, limitation and good faith in the context of FIDIC Sub-Clauses 20.1 and 3.5.

United KingdomReal Estate and Construction

Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016

The Dubai International Finance Centre ("DIFC") Court of Appeal has recently handed down a judgment in which it considered issues such as notices as conditions precedent, limitation and good faith in the context of FIDIC Sub-Clauses 20.1 and 3.5. We summarise the case and review its potential implications below.

The Facts

On 11 July 2017, the Employer, Panther Real Estate Development LLC ("Panther"), entered into a contract (the "Contract") with Modern Executive Systems Contracting LLC ("MESC"), the Main Contractor, for the construction and completion of a residential tower building in Dubai. The Contract was based on the FIDIC Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer (First Edition, 1999), as amended by the Particular Conditions and other detailed provisions. The governing law of the contract was DIFC

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from