Panther Real Estate Development LLC v Modern Executive Systems
Contracting LLC [2022] DIFC CA 016
The Dubai International Finance Centre
("DIFC") Court of Appeal has recently
handed down a judgment in which it considered issues such as
notices as conditions precedent, limitation and good faith in the
context of FIDIC Sub-Clauses 20.1 and 3.5. We summarise the case
and review its potential implications below.
The Facts
On 11 July 2017, the Employer, Panther Real Estate Development
LLC ("Panther"), entered into a contract
(the "Contract") with Modern Executive
Systems Contracting LLC ("MESC"), the
Main Contractor, for the construction and completion of a
residential tower building in Dubai. The Contract was based on the
FIDIC Conditions of Contract for Construction for Building and
Engineering Works Designed by the Employer (First Edition, 1999),
as amended by the Particular Conditions and other detailed
provisions. The governing law of the contract was DIFC