Last year saw a number of cases concerning good faith in
construction contracts. As parties increasingly use concepts
such as "good faith" and "reasonableness" in
their contracts, further judicial examination of these concepts is
likely; what did we learn about them in 2013?
In TSG
Building Services Plc v South Anglia Housing Limited the
parties' TPC 2005 contract provided that they were to work
together and individually in the spirit of trust, fairness and
mutual co-operation. It further stated that "in all
matters governed by the Partnering Contract they shall act
reasonably and without delay".
The parties fell out. The contract included a termination
clause which either party could exercise on 3 months' notice (a
so called "termination at will" provision). South
Anglia wrote to TSG giving 3 months' notice to terminate the
contract. No reasons were given.