In February 2017, in Carillion Construction Ltd v Emcor Engineering Services Ltd,1 the Court of Appeal had the opportunity to consider a novel issue in relation to extensions of time: how extensions of time after the date for completion are applied.

United KingdomReal Estate and Construction

In February 2017, in Carillion Construction Ltd v Emcor Engineering Services Ltd,1 the Court of Appeal had the opportunity to consider a novel issue in relation to extensions of time: how extensions of time after the date for completion are applied.

As Andrew Weston explains below, this was a case in which a question was raised about whether an extension of time awarded under a subcontract should be contiguous or non-contiguous.

The essential issue for the Court to decide, where an extension of time is granted after the date for completion under a standard DOM/2 form of subcontract, was whether it must commence on what was the date for completion (i.e. a contiguous extension of time) or when the delay occurs (i.e. a non-contiguous extension of time).