Did You Miss? Sheffield City Council V Scotfield Group Limited, Camstead Limited

Gatehouse Chambers
Gatehouse Chambers
Contributor
Gatehouse Chambers

Gatehouse Chambers

Gatehouse Chambers is a leading commercial set with expertise spanning commercial dispute...

View firm profile
Explore more from Gatehouse Chambers

C and D1 had entered a contract for sale of a development site in March 2019 for a price of £2.565 million. The contract was a detailed contract to allow C, the local authority...

United KingdomReal Estate and Construction

The facts

C and D1 had entered a contract for sale of a development site in March 2019 for a price of £2.565 million. The contract was a detailed contract to allow C, the local authority, to have control over the development of land sold.

The contact was a conditional subject to Satisfactory Planning Permission. It also included an obligation that D1 had to provide C with evidence of a bone fide arm's length construction contract and if on the expiry of the Long Stop Date such evidence had not been provided "the Long Stop Date shall be extended until such evidence is provided" (clause 24.5). C requested evidence of the Building Contract but was not satisfied with the documents provided by D1. C therefore served notice on D1 terminating the contract claiming there had been a substantial breach. D1 countered by serving a notice to complete. C then issued the claim seeking, amongst other things, a declaration that the contract had been terminated and that C was

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from