ARTICLE · 03 JANUARY 2018

Design Obligations: Fitness For Purpose

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

As Karen Gidwani explains, this year brought the conclusion to the long-running case of MT Højgaard A/S v. E.ON Climate and Renewables UK Robin Rigg and another ("MTH v. E.ON"). Fenwick Elliott acted for MTH.

United KingdomReal Estate and Construction

As Karen Gidwani explains, last year brought the conclusion to the long-running case of MT Højgaard A/S v. E.ON Climate and Renewables UK Robin Rigg and another ("MTH v. E.ON")1. Fenwick Elliott acted for MTH.

This was a case concerning the principles of contract interpretation in the context of a fitness for purpose clause. It was finally decided by the Supreme Court in E.ON's favour. This article focusses in more detail on some of the arguments made by MTH and the treatment of those arguments by the Supreme Court.

A key issue to consider with this case is whether there is a trend now by the courts to take a more literalist approach to the interpretation of contracts. This is a trend that has been denied recently by the Supreme Court in Wood v. Capita Insurance Services Ltd2, but in some of the cases that have emerged since Arnold v. Britton3 (decided after the Court of Appeal decision in MTH v. E.ON) the court does appear to be more willing to look at the letter