In 2019 the construction industry was thrown into a state of confusion (before COVID or BREXIT had a chance to try) by a Court of Appeal ("COA'")...

United KingdomReal Estate and Construction

In 2019 the construction industry was thrown into a state of confusion (before COVID or BREXIT had a chance to try) by a Court of Appeal ("COA'") decision turning on its head the long held "orthodox" view that liquidated damages ("LDs") for incomplete works would only accrue until contract termination, not to completion of the works.

On appeal of this decision in Triple Point Technology Inc (Triple Point) v PTT Public Company Ltd (PTT) [2021] UKSC 29  the UK Supreme Court ("UKSC"), in its eagerly awaited judgment, has provided some much needed clarity to the industry on the applicability of LDs until termination. The UKSC unanimously held that LDs would indeed only apply up to termination of a contract, irrespective of whether the works were completed by the Contractor or accepted by the Employer. The UKSC held that to accept otherwise was "inconsistent with commercial reality and the accepted function of liquidated damages".