The Court of Appeal has dismissed an appeal against a Commercial
Court decision that a buyer was entitled to the repayment of an
advance where there had been non-delivery for force majeure
reasons. In doing so, the court found that, as a matter of
construction, the contract between the parties obliged the seller
to make repayment in the circumstances, both because that was the
natural meaning of the language and because a different
construction would offend business common sense: Nord Naphtha Limited v New Stream Trading
AG [2021] EWCA Civ 1829.
Whilst the force majeure event in this case was unrelated to
COVID-19, the decision will be of interest to financial
institutions considering the ongoing impact of the pandemic. Of
note is the Court of Appeal's comment that it would be
"surprising" if a contract for the sale of goods did not
include a provision requiring the return of an advance payment in
the event of non-delivery. The court considered this to be