Court Considers Complex Issue Of Concurrent Delay: Thomas Barnes & Sons Plc v Blackburn With Darwen Borough Council

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

In this TCC decision, the Court considered the complex issue of concurrent delay and whether the Council had followed the correct termination procedure under the contract, and whether this termination was effective.

United KingdomReal Estate and Construction

In this TCC decision, the Court considered the complex issue of concurrent delay and whether the Council had followed the correct termination procedure under the contract, and whether this termination was effective.

The Council appointed Thomas Barnes ("TB") (in administration) to build Blackburn bus station.

There were severe delays on the project, for which TB claimed extensions of time ("EOT"). The Council ultimately terminated the contract because of the delays and the administrators for TB brought proceedings contesting the termination, seeking to establish a right to EOT, and claiming loss and expense and damages for wrongful termination.

The key dispute related to the allegation that works following the erection of structural steelwork were delayed because of deflection and associated issues requiring remedial works, which caused a delay to the critical path, where it was alleged that the Council was responsible for the steelwork design. However,

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from