In this TCC decision, the Court considered the complex
issue of concurrent delay and whether the Council had followed the
correct termination procedure under the contract, and whether this
termination was effective.
The Council appointed Thomas Barnes ("TB") (in
administration) to build Blackburn bus station.
There were severe delays on the project, for which TB claimed
extensions of time ("EOT"). The Council ultimately
terminated the contract because of the delays and the
administrators for TB brought proceedings contesting the
termination, seeking to establish a right to EOT, and claiming loss
and expense and damages for wrongful termination.
The key dispute related to the allegation that works following
the erection of structural steelwork were delayed because of
deflection and associated issues requiring remedial works, which
caused a delay to the critical path, where it was alleged that the
Council was responsible for the steelwork design. However,