ARTICLE · 12 MARCH 2012

Contractor Monthly - Pay Less Notices, The Confusion Clarified

The Construction Act states that a pay less notice must specify ‘the sum that the payer considers to be due on the date the notice is served' (S111(4)(a)).

United KingdomReal Estate and Construction
Kim Teichmann
Kim Teichmann

The Construction Act states that a pay less notice must specify 'the sum that the payer considers to be due on the date the notice is served' (S111(4)(a)).

There has been confusion as to whether this refers to the sum that was due at the due date or whether a further valuation is required to take account of work done between the due date and the date of the pay less notice.

We believe the pay less notice should set out the sum which was due at the payment due date and any deductions to be made from it.

The answer lies in the use of the word 'due'. Most contracts will provide for the payment due on each due date to be for work done in the period leading up to it. Payment for further work done after that date will become due on later dates. Accordingly, when a pay less notice is given between due dates, the only sum due for work done will be that which was due at the last date, and payment will not yet be due for work done since then. The sum due at the date of