The Construction Act states that a pay less notice must specify
'the sum that the payer considers to be due on the date the
notice is served' (S111(4)(a)).
There has been confusion as to whether this refers to the sum
that was due at the due date or whether a further valuation is
required to take account of work done between the due date and the
date of the pay less notice.
We believe the pay less notice should set out the sum which was
due at the payment due date and any deductions to be made from
it.
The answer lies in the use of the word 'due'. Most
contracts will provide for the payment due on each due date to be
for work done in the period leading up to it. Payment for further
work done after that date will become due on later dates.
Accordingly, when a pay less notice is given between due dates, the
only sum due for work done will be that which was due at the last
date, and payment will not yet be due for work done since then. The
sum due at the date of