ADJUDICATION
See Quietfield v Vascroft Contractors under Keating Chambers Reported Cases on failure to consider new evidence in subsequent adjudication.
Time limits for referral
Hart Investments Ltd v Fidler
[2007] 109 Con LR 67 TCC, [2007] TCLR 1 and
[2007] BLR 30.
Already reported in CILL and noted in KC in Brief January 2007. The TCC held invalid a referral notice served eight, rather than seven, days after the notice of intention to refer under paragraph 7 of the Scheme for Construction Contracts. This decision departs somewhat from statements in English cases such as
Barnes & Elliott v Taylor Woodrow and
Simons v Aardvark (Paul Darling QC) in favour of the stricter approach to time limits of Scottish cases such as
Ritchie Bros v Philp. See now also
Epping Electrical v Briggs & Forrester (David Thomas QC).