Construction Contract Notice Provisions Held To Be Conditions Precedent To Contractor's Claims For Loss And Expense

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

The Scottish Court of Session upheld in FES Limited v HFD Construction Group Ltd that notice provisions in construction contracts can act as conditions precedent to claims for loss and expense if explicitly stated, emphasizing strict compliance requirements.

United KingdomReal Estate and Construction

The Inner House (appeal division) of the Scottish Court of Session held in FES Limited v HFD Construction Group Ltd that a contractor was not entitled to claim for loss and expense as it had not followed the notice provisions under a construction contract.

The Inner House (appeal division) of the Scottish Court of Session determined in FES Limited v HFD Construction Group Ltd that notice provisions under a construction contract were conditions precedent to a contractor's entitlement to reimbursement for loss and expense.

Background

In 2020, FES Limited (FES) and HFD Construction Group Ltd (HFD) contracted to fit out an office building on Bothwell Street in Glasgow.

The parties' contract was an amended version of the Scottish Building Contract Committee (SBCC) Standard Building Contract with Quantities for use in Scotland, 2016 Edition (SBC/Q/Scot 2016), based on Joint Contract Tribunal (JCT) conditions.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from