1. S&T (UK) Limited v Grove Developments [2018] EWCA Civ
2448
Grove employed S&T to design and build a new hotel at
Heathrow Airport under a JCT Design and Build Contract. In response
to an interim payment application by S&T, Grove issued a
payment notice which had clearly set out the basis of the
valuation, however it was issued late. Grove then issued a pay-less
notice which, although issued on time, did not provide the detailed
calculation of the basis of the valuation. S&T disputed that it
was a valid pay-less notice because they said it did not set out
the basis for the sum due, a requirement for a pay-less