A party wishing to refer a dispute to adjudication will generally be required by the terms of the construction contract to issue his notice of referral to the adjudicator selected by the prescribed nomination body.

United KingdomReal Estate and Construction
Julie Scott
Julie Scott

A party wishing to refer a dispute to adjudication will generally be required by the terms of the construction contract to issue his notice of referral to the adjudicator selected by the prescribed nomination body. What happens when the referring party is unhappy with the adjudicator selected by the nominating body? Can he go through the nomination procedures as many times as he wants to until an adjudicator acceptable to him is selected?

These are the issues that were considered in the recent Technology and Construction Court decision of Lanes Group plc v Galliford Try Infrastructure Limited [2011].

Lanes Group Decision

In this case Galliford Try decided not to proceed to issue its notice of referral to an adjudicator nominated by the ICE. It would seem that this was because of exchanges between the solicitor for Galliford Try and the nominated adjudicator in a previous but unrelated adjudication. Galliford Try went through the nomination procedures again and an

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.