1. Pre-action conduct
Claims which are worth £25,000 or less are subject to a
Compulsory Pre-Action Protocol. If there is no admission of
liability or if parties cannot then agree quantum court proceedings
can be raised.
There are currently no compulsory protocols for claims worth
over £25,000 or for industrial disease or medical negligence
claims.
2. Time-bar
Subject to certain exceptions there is a three year time-bar for
personal injury claims. Time-bar is interrupted through service,
not the issue, of proceedings. This can be significant if the
compensator is based in a country which does not recognise postal
service of court proceedings.
The court has an equitable discretion to allow claims raised out
with the three year deadline per section 19A of the Prescription
and Limitation (Scotland) Act 1973 with the test being the balance
of prejudice to the parties.