Share on LinkedInShare on LinkedIn

ARTICLE · 22 JANUARY 2020

Commercial Sense Prevails Once Again In The Court Of Appeal

It's always good to see the courts taking a common and commercial sense approach and seeking, as far as possible, to honour the bargain made by the parties.

United KingdomReal Estate and Construction

Bennett (Construction) Ltd v CIMC MBS Ltd (formerly Verbus Systems Ltd) [2019] ("Bennett")

It's always good to see the courts taking a common and commercial sense approach and seeking, as far as possible, to honour the bargain made by the parties. It's particularly encouraging in the construction industry to see this when it comes to the much disputed and discussed payment sections of the Housing Grants, Construction and Regeneration Act 1996 (the "Act") and the Scheme for Construction Contracts 1998 (the "Scheme").

That is exactly what happened recently in the Bennett case in the Court of Appeal. Milestone payments were found to be compliant with the Act and the implied payment terms in the Scheme were found to be capable of co-existing with the payment provisions of the contract (and not requiring wholesale replacement) - the two central issues to the case - thereby doing the least violence to the agreement between the parties.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.