Bennett (Construction) Ltd v CIMC MBS Ltd (formerly Verbus
Systems Ltd) [2019] ("Bennett")
It's always good to see the courts taking a common and
commercial sense approach and seeking, as far as possible, to
honour the bargain made by the parties. It's particularly
encouraging in the construction industry to see this when it comes
to the much disputed and discussed payment sections of the Housing
Grants, Construction and Regeneration Act 1996 (the
"Act") and the Scheme for Construction
Contracts 1998 (the "Scheme").
That is exactly what happened recently in the Bennett case in
the Court of Appeal. Milestone payments were found to be compliant
with the Act and the implied payment terms in the Scheme were found
to be capable of co-existing with the payment provisions of the
contract (and not requiring wholesale replacement) - the two
central issues to the case - thereby doing the least violence to
the agreement between the parties.