Commercial Management (Investments) Ltd v Mitchell Design and Construct Ltd And Another [2016] EWHC 76 (TCC)

Here the court considered the application of the Unfair Contract Terms Act 1977 (UCTA) to a set of standard subcontract terms.

United KingdomReal Estate and Construction

Here the court considered the application of the Unfair Contract Terms Act 1977 (UCTA) to a set of standard subcontract terms. The contractor, Mitchell was engaged to design and build a warehouse.  It subcontracted ground treatment works to a sub-contractor, Regorco (formerly Roger Bullivant).  The works were completed, and the warehouse was subsequently acquired by Commercial Management.  They brought a claim against Mitchell and Regorco (under a collateral warranty) following settlement of the warehouse slab.

The court considered a number of preliminary issues governing the subcontract between the parties, in particular whether Regorco's standard terms had been incorporated into the sub-contract, and if so whether UCTA applied and if so whether clause 12(d) limiting the time in which claims might be brought was reasonable. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from