ARTICLE · 10 JULY 2002

Changes to the JCT Standard Form of Building Contract 1998 Edition

United KingdomReal Estate and Construction

This article contains a brief summary of some of the changes made by JCT ‘98 Amendment 4 (Amendment 4) to the JCT Standard Form of Building Contract 1998 Edition (the Contract). These changes were issued in January 2002 and apply to Clause 25 (extension of time), Clause 26 (loss and expense) and Clause 30 (certificates and payment). The amendment to Clause 30 applies to private JCT contracts only.

New "relevant event" for EOT claims

Pursuant to Amendment 4 a new definition of relevant event for extension of time claims has been added to Clause 25:

"25.4.19 – Save as provided for in Clause 25.4.1 to 25.4.18 any impediment, prevention or default, whether by act or omission, by the employer or any person for whom the employer is responsible except to the extent that it was caused or contributed to by any default, whether by act or omission, of the Contractor or his servants, agents or sub-contractors."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from