Ch-Ch-Changes - Can They Be Made To Infrastructure Projects Post Application?

The issue of an applicant changing a project after it has been applied for has been an ongoing one and has cropped up in many, if not most, current applications.

United KingdomReal Estate and Construction

Today's entry considers the ability to make changes to projects after applications have been made.

There are three sorts of changes that might be possible after an application for a major infrastructure project has been made:

  • changes before or during the examination supported by the applicant
  • changes during the examination not supported by the applicant, and
  • changes after the decision.

I'll have a look at where I think we are on each of these.

Changes during the examination supported by the applicant

The issue of an applicant changing a project after it has been applied for has been an ongoing one and has cropped up in many, if not most, current applications. The bar below which changes are acceptable and above which they aren't has still yet to be defined clearly though. Paragraph 106 of the guidance on examinations is rather unhelpful on this point as it seems to set two different thresholds in consecutive sentences: